4th Street CCLIP Resurfacing Project
4th Street CCLIP Resurfacing Project
Project Number: City of Leavenworth: 2023-027 – KDOT: 052 U-2509-01
Location: 4th Street (US-73/K-7) (Rees to Poplar)
Description of Work:
- Asphalt Pavement Resurfacing of 4th Street/US-73/K-7. Portion of street segment will be a 2” mill & overlay while another portion will be a 3” mill & overlay. In accordance with Federal ADA requirements, sidewalks and ADA compliant ramps to be reconstructed. Broken curbs & gutters will be reconstructed. After completion of the asphalt overlay, manholes will be cut out and adjusted to correct height then a “diamond” of concrete will be poured around them. Finally Pavement Markings will be placed.
Design Firm: JEO
Construction Contract: J. M. Fahey
Inspection Firm: JEO
Project Start Date: March 17, 2025
Project Completion Date: June 15, 2025 (90 Calendar Days)
Project Costs:
- Design = $76,500 (Proposed)
- Construction = $455,987.75 (Bid)
- Inspection = $72,565 (Proposed)
Funding:
- KDOT CCLIP Grant for up to $400,000
- KDOT Pays 85% - City Pays 15% (Participating Line Items)
- City Pays 100% (Non-Participating Line Items)